‘Fully committed’: Midlands hospice in Offaly remains ‘a priority project’ for HSE


HSE says it is 'fully committed to delivering this project' in Tullamore 'and engaging with all parties as part of this next development phase and are working to provide a definitive timeline as quickly as possible'
The Midlands hospice remains a priority project for the HSE and will provide specialist inpatient palliative and end-of-life care for patients and families across Laois, Offaly, Westmeath and Longford closer to home.
In a statement issued to the Tribune this week, the HSE says: "Planning permission has been secured in May this year and progress has been made to date. The project is currently progressing through the next stages of development in terms of design and delivery to ensure every euro invested contributes as effectively as possible to high-quality, sustainable hospice care while maintaining the project's core vision and benefits for patients and families.
"The HSE Dublin and Midlands Region are fully committed to delivering this project and engaging with all parties as part of this next development phase and are working to provide a definitive timeline as quickly as possible. The objective remains to deliver a modern hospice facility that meets the long-term needs of people across the Midlands."
Offaly Fianna Fáil TD Tony McCormack says there must now be a clear path to construction with no further delays or roadblocks.
The planned 20-bed hospice at Arden Lane in Tullamore will provide specialist palliative and end-of-life care for patients across Offaly, Laois, Westmeath and Longford.
The Midlands remains the only region in Ireland without a dedicated inpatient hospice facility.
Deputy McCormack said the HSE's renewed commitment is very welcome and provides reassurance to families across the region.
"I welcome the clear commitment from the HSE that the Midlands Hospice remains a priority and that they are fully committed to delivering it.
"This is a hugely important project for the entire Midlands. It will allow people facing the most difficult time in their lives to receive specialist care close to home, surrounded by family and friends.
"We have made significant progress in getting this project to where it is today, and we now need to build on that progress. We cannot afford any more stumbles or roadblocks."
The HSE has confirmed that the project is progressing through the next stages of design and delivery and that it is working to provide a definitive timeline as quickly as possible.
However, concerns have been raised following confirmation that the estimated cost has increased from €24 million to approximately €40 million.
Deputy McCormack said rising construction costs underline the importance of moving ahead without further unnecessary delays.
"I have said before that the cheapest time to build this hospice was yesterday. Every delay risks adding further costs, but more importantly, it means patients and families are left waiting for a service that should already be available in our region.
"The planning process has been progressed, the need is clearly established and the HSE has reaffirmed its commitment. What we need now is certainty on funding, a clear timeline and construction to get underway."
Deputy McCormack has raised the project directly at the Oireachtas Infrastructure Committee and has consistently pressed for its delivery.
He said the focus must now be on ensuring the project moves forward without further obstacles.
"This hospice is not a luxury. It is an essential healthcare facility that the people of the Midlands have needed for many years.
"I welcome the HSE's commitment and look forward to working with all involved to see it delivered.
"We have waited long enough. Now is the time to turn that commitment into construction and ultimately into a hospice that will provide dignity, comfort and care for patients and their families across the Midlands," Deputy McCormack concluded.